Permanent Realignment of an Operating High Pressure Petroleum Product Pipeline Through HDD
Humkhad Nala at Chainage 49.07 km of the PAJPL Una Branch Pipeline experienced recurring washouts during successive monsoon seasons, necessitating permanent realignment of the affected section. A single 854 m Horizontal Directional Drilling (HDD) crossing was constructed, placing the 12.75-inch OD pipeline at a maximum depth of approximately 55 m below the original ground level and approximately 40 m below the most recently scoured nala bed. The work was executed on the live, pressurized pipeline without interruption of product supply. The alignment comprised approximately 90% boulder formation, requiring enhanced drilling capacity and ARO over the 3LPE coating. The pipe string was fabricated in two sections to minimize surface disturbance. During hook-up, a controlled method was developed to address dimensional issues with 2-inch LOR vent plugs. Approximately 65 KL of HSD was evacuated from the old section, including 25 KL transferred directly to the HSD storage tank. The paper presents the engineering measures, operational constraints and key lessons from the project.