Appeals Court Ruling Threatens 2027 In-Service Date for $1B Natural Gas Pipeline

By Daniel Onyango
Time to read: 1 minute
Court gavel on court desk (© Adobe Stock/BillionPhotos.com)
Court gavel on court desk (© Adobe Stock/BillionPhotos.com)

As the deadline ticks toward the 2027-28 winter heating season, a crucial energy Lifeline for New York City and Long Island hangs in the balance, caught between the demands of regional energy security and strict environmental compliance.

A federal appeals court rejected a bid by energy developer Williams Cos. to keep a vital New Jersey environmental permit active for its $1-billion Northeast Supply Enhancement natural gas pipeline project.

The U.S. Court of Appeals for the Third Circuit in Philadelphia denied a petition from Williams unit Transcontinental Gas Pipe Line Co. to rehear a decision vacating New Jersey’s water-quality certification.

The ruling returns the certification to the New Jersey Department of Environmental Protection (NJDEP), which must decide whether to issue a revised approval, request further analyses, or reach a different outcome.

Without a valid state certification, the Federal Energy Regulatory Commission cannot grant authorization for New Jersey construction, directly threatening the project's timeline.

The 37-mile expansion project is designed to increase capacity by 400,000 dekatherms per day to serve National Grid customers in New York City and Long Island.

Transco warned the court that losing the approval delays New Jersey construction, originally set for Oct. 1, and jeopardizes its target Nov. 1, 2027 in-service date for the 2027-28 winter heating season.

Transco highlighted New Jersey infrastructure as a critical-path component, particularly Compressor Station 206 in Somerset County, which requires 13 months to build.

The project also encompasses the 3.4-mile Madison Loop in Middlesex County and six miles of offshore pipeline in Raritan Bay.

While environmental challenges focused on Raritan Bay dredging impacts, the court's order vacates the permit covering all New Jersey components.

Judges previously found NJDEP failed to explain how dredging would comply with water quality standards and left monitoring rules unresolved.

Transco requested the court allow the permit to remain active while NJDEP addressed the issues, but the panel denied the request without granting a deadline for state action.

"The court's decision vacating the water quality certification stands and construction in New Jersey cannot go forward," said Christopher Miller, executive director of the Eastern Environmental Law Center.

While New York and Pennsylvania permits remain intact, New Jersey work remains halted absent further judicial intervention or Supreme Court review.