GasNet Nears Completion of $3.2 Million High-Pressure Pipeline Upgrade Near Jihlava

By Daniel Onyango
Time to read: 1 minute
Pipelayer at a construction site in the forrest (© Shutterstock/Maksim Safaniuk)
Pipelayer at a construction site in the forrest (© Shutterstock/Maksim Safaniuk)

GasNet Group, Czechia’s largest gas distributor, is finalizing the reconstruction of a critical trunk high-pressure gas pipeline near Jihlava.

The 74 million Czech koruna ($3.2 million) investment aims to bolster long-term supply reliability for more than 116,000 customers across the Vysočina Region.

Crews began reconstructing the 3,600-meter steel pipeline this spring as part of a systematic modernization of the Prague–Znojmo trunk route. Originally constructed in the 1940s, the old pipeline ran directly through the built-up Bedřichov district.

To accommodate future urban development and reduce disruption to residents, engineers rerouted the new pipeline outside populated areas, running roughly parallel to the E59 highway.

To prevent traffic interference where the pipeline crosses the E59, workers utilized trenchless guided boring beneath the road surface. Specialized technical measures also ensured uninterrupted gas service throughout construction for local households, businesses, and industrial zones.

"While planning the project, we looked for ways to maintain stable gas supplies throughout construction," said Pavel Komsa, director of investment and construction at GasNet Group. "We ultimately achieved this through appropriately selected technical measures."

The pipeline is undergoing hydrostatic pressure testing to verify structural strength and tightness prior to its scheduled November commissioning. Engineers filled the gas-free pipeline with 240 cubic meters of municipal water, gradually raising the pressure to confirm system integrity.

"Water is safer than air for pressure testing," explained Stanislav Bejr, head of construction management at GasNet Group.

"If a leak were to occur, only a small amount of water would escape and the pressure would drop more quickly, significantly reducing risks." Following the test, the clean water will be discharged into stormwater sewers, and the pipeline will undergo thorough mechanical drying.

The Jihlava project forms part of GasNet’s broader network overhaul across Czechia. In 2026, GasNet and its subsidiary, Gas Distribution, plan to invest at least 6.5 billion koruna to modernize roughly 286 kilometers of pipelines and 49 regulator stations statewide.

Final site landscaping around the Jihlava route will conclude by 2027.