Restarting a Pipe Coating Plant: Lessons from CPC’s Return to Operations

By Constantin Schreiber
Posted in:
Time to read: 4 minutes

An Interview with Toghrul Mahmudov, Acting Director of CPC

Toghrul Mahmudov, Acting Director of CPC (©CPC)
Toghrul Mahmudov, Acting Director of CPC (©CPC)

After a prolonged period of uncertainty and standby, Caspian Pipe Coatings LLC (CPC) returned to full production in 2026 and completed approximately 26 km of concrete weight coating for a 20-inch offshore pipeline scope. The production campaign was completed in 43 production days, ahead of an original plan of approximately two months.

In this interview, Toghrul Mahmudov, Acting Director of CPC, shares his experience of navigating operational uncertainty, rebuilding commercial activity, remobilizing personnel and equipment, and successfully returning the plant to production.
 

For readers who may not be familiar with CPC, could you briefly introduce the company and its role in the Caspian pipeline market?

CPC is an Azerbaijan-based pipe coating company established in 2002. The plant was developed to support major oil and gas pipeline projects in Azerbaijan and the wider Caspian region and has coated approximately 3,000 kilometers of pipelines since its establishment. Its capabilities include anti-corrosion coating, concrete weight coating, thermal insulation coating, and other specialized pipe coating solutions. Over the years, CPC has participated in a number of major regional projects. What makes the recent period particularly interesting, however, is not only what we produced, but how we returned to production after a prolonged standby period.
 

What led CPC into standby in the first place?

The turning point came in 2023, when CPC was informed that the existing plant would eventually need to be relocated because of planned urban development and road infrastructure works in the surrounding area.

For an industrial facility of this type, relocation is a major decision. It requires suitable land, logistics access, utilities, storage capacity, and substantial capital investment. At that stage, there was no immediate decision from the shareholders on where or when the plant would move.

We therefore had to protect the financial stability of the company while that uncertainty continued. Personnel numbers were significantly reduced, costs were optimized, and the company moved into a standby model. The objective was to keep the business financially sustainable until a longer-term decision could be made.
 

How do you put a coating plant into standby without losing the ability to restart it later?

That was probably the most important question during the standby period. There is a big difference between shutting down a plant and preserving a plant in a condition where it can realistically operate again.

We had to reduce costs, but at the same time we could not allow the technical capability to disappear. Certain maintenance activities still had to continue. Equipment condition had to be monitored. Documentation and operating knowledge had to be retained. We also needed to maintain contact with experienced people who had worked at the plant before.

You can replace equipment, but practical knowledge is much harder to replace quickly. So the challenge was always to find the right balance: reduce expenditure enough to remain financially stable, but not so aggressively that a future restart would become more expensive or, in practice, impossible.
 

When did the strategy change from simply preserving CPC to actively returning to the market?

That changed in early 2025. We received clarity that CPC could remain at its existing location, particularly in view of two strategically important projects for Azerbaijan’s oil and gas industry: the Shah Deniz Gas Compression and the Absheron Full Field Development projects. At the same time, the company was given the opportunity to actively pursue new business opportunities in the market.

From that point, our focus changed. We were no longer only managing standby. We had to rebuild commercial momentum.

We started actively reviewing pipeline developments in Azerbaijan and across the Caspian region. We looked at upcoming projects, pipe diameters, coating requirements, schedules, and where our existing plant could genuinely be competitive. We restarted discussions with clients and became much more active in business development and market analysis.

That work was important because it would not have made sense to fully remobilize the plant without a real project. The commercial opportunity had to come first or at least develop in parallel with technical preparation.
 

How did that business development effort turn into the 2026 production campaign?

By the second half of 2025, one of the opportunities we had been pursuing became concrete. We entered discussions with SOCAR's Azneft Production Union regarding concrete weight coating for an offshore pipeline project.

Those discussions continued into the end of the year, and in February 2026, CPC was awarded the coating contract. The scope was approximately 26 kilometers of 20-inch pipe requiring concrete weight coating.

For us, signing the contract was a major commercial milestone, but it immediately created an operational challenge. We now had to prove that a plant that had spent a prolonged period in standby could be brought back into production within the project schedule.
 

What were the main operational challenges in bringing the plant back?

The first challenge was people. During standby we had reduced the workforce considerably, so we had to rebuild the production organization. Where possible, we brought experienced former personnel back, and we recruited additional people where required. Having people who already understood the equipment and the production process helped us a great deal because it shortened the learning curve.

The second challenge was equipment readiness. Maintenance had continued during standby, but naturally not at the same level as during continuous production. We therefore did not assume that the plant was ready simply because equipment could be switched on.

We went step by step. Equipment was inspected, necessary maintenance and repairs were completed, individual systems were checked, and then we moved into dry runs and operational testing. That stage was critical. A plant can look perfectly acceptable during a static inspection, but once equipment begins running continuously, different issues appear. Dry runs allowed us to identify and correct those issues before they became production problems.

The whole exercise had to be completed in a relatively compressed period, so commercial, technical, maintenance, and personnel mobilization activities had to move together.
 

What was the final result, and what do you think other industrial operators can take from the CPC experience?

Once operational readiness was confirmed, we moved into full production. The original production plan was approximately two months. We completed the 26-kilometer concrete weight coating scope in 43 production days, ahead of that plan. Despite thorough preparation, we still encountered unexpected technical challenges, particularly with spare parts, which occasionally resulted in short production stoppages. What I am particularly proud of is how our team worked overtime, found practical solutions, and resumed production while keeping the overall schedule and budget under control.

For us, the important point is not only the number of kilometers or the 43 days. The project demonstrated that CPC had completed the entire journey from standby back to a functioning industrial operation: business development, contract award, remobilization, recruitment, maintenance, testing, production, and successful completion.

There are several lessons I would take from the experience. First, if there is any possibility that an industrial facility may operate again, restart should be considered from the first day of standby. Decisions taken during the standby period determine how difficult the return will be.

Second, retaining access to experienced people is extremely important. Technical knowledge accumulated over many years cannot always be rebuilt within a project mobilization period.

Third, commercial and operational teams have to work very closely. There is little value in fully remobilizing an industrial asset without a market opportunity, but equally, business development cannot commit to a project without understanding what the plant can realistically deliver.

CPC is continuing to pursue additional opportunities in Azerbaijan and the wider Caspian region. The 2026 campaign gave us confidence that the plant can respond when the right project emerges.

For me, the main lesson is simple: preserving an industrial asset is not just about maintaining equipment. It is about preserving the ability to operate again.